Posted on: July 13, 2016

7/13 Update

Nicor Downtown Construction Update: Main installation has finished in the 300 block. Service installation will begin today and continue throughout the week. Street and sidewalk restoration will follow shortly after the completion of service installation. ...Read on...

Posted on: June 22, 2016

6/22 Update

Phase Map

Final asphalt paving between 1st and 2nd streets will be completed 6/21 (orange phase of the map). Later this week concrete restoration in the alley behind the businesses on the south side of Route 38 will begin as well as sidewalk repairs between 1st and...Read on...

Additional Info...
Posted on: May 26, 2016

5/26 Update

Downtown Phase Map

Beginning after the Memorial Day weekend, Nicor Gas Contractor crews will begin the installation of a new gas main along the North-side of Route 38 between 1st and 2nd street (orange phase of the map). A single lane of traffic will be closed, resulting in...Read on...

Additional Info...
Posted on: May 19, 2016

5/19 Update

Locust Construction

This week and through the end of the month, Nicor Gas contractor crews will begin new gas main installation along Locust Street (area marked with a yellow rectangle on the map). Barring any unforeseen weather events or other delays, restoration will begin...Read on...

Additional Info...
Posted on: May 12, 2016

5/12 update

Grove Corridor

Over the next several weeks Nicor Gas contractor crews will begin the installation and connection of new services to the newly installed gas mains south of Route 38 (see map). Restoration efforts will begin soon after. Nicor is taking the approach of inst...Read on...

Enlarged Map